Shanahan Engineering is a world-class Energy Construction company with over 35 years’ proven experience in Construction, Commissioning and Plant Operation on large scale power projects worldwide. We have a proven track record of creating value for our customers and delivering innovative solutions. With involvement in over 400 international power generation projects in over 55 countries, Shanahan Engineering continues to be responsible for the delivery and start-up of some of the world’s largest power stations.

  • SEL is delighted to have been chosen by Tecnicas Reunidas to undertake the full erection and assembly of Doosan DST-S20 Steam Turbine and Generator and associated auxiliary systems inclusive of;

  • Bearing Pedestals installation

  • Base plates installation and levelling using fixators (supplied by others), block base and anchor bolts

  • Setting the base plates, Steam Turbine LP hood setting and erection according to Manufacturers guidelines

  • Alignment (to be done together with ST final alignment)

  • Main Steam and Extraction Steam Pipe Erection, Auxiliary Pipe Erection

  • Oil Flushing (to be done together with Gen oil flushing)

  • Final Alignment (to be done together with ST final alignment)

  • Coupling of Rotors

  • Erection of Insulation, Enclosure and Painting

  • Installation of instrumentation